Construction Results
Major Works in Japan
Wind Power Generation at Hibikinada (Fukuoka Pref.)
Construction Term : 2002/9 ~ 2003/3
Contents of the Project
Rating Output : 1,500kw x 10Nos.
Tokyo International Airport (Tokyo Metropolis)
Construction of Runway D etc Tokyo International Airport
Construction Term : 2005/3 ~ 2010/9
Contents of the Project
Revetment Reclamation :
Sand Compaction=11,164 Nos
Sand Drain=41,660 Nos
Sand Mat=832,667m³
Reclamation=4,119,992m³
Jetty Construction :
Piling Work=518 Nos
Jacket Installation Work=88Nos
Floor Slab Work=235,610m²
Revetment for Reclamation of Devastation Countermeasure at Unzen (Nagasaki Pref.)
Construction Term : 1993/3 ~ 1994/3
Contents of the Project
Excavation for Foundation=44,740 m³
Riprap Work=21,772 m³
Manufacture & Install of Calcite=90 Nos
Manufacture & Install of Armor Block=810 Nos
Manufacture & Install of Precast Block=150 Nos
Backfilling of Rubble Stone=33,740 m³
Superstructure Work=288m
Ancillary Work=288m
Tunnel at Hachinohe (Aomori Pref.)
Construction Term : 2002/3 ~ 2006/12
Contents of the Project
NATM Method (Inner Cross Section 68㎡) =240m
Bridge Substructure of No.2 Meishin Expressway at Kirigataki (Mie Pref.)
Construction Term : 1999/3 ~ 2001/12
Contents of the Project
Length of Bridge=322m
Soil Cutting Work=34,257 m³
Bridge Foundation Work(Deep Pileφ3.0~14.5)=200m
Bridge Substructure Work=11Nos
Temporary Jetty Work=5,248m²
Residential Land Development at Yurigaoka, Umi Town (Fukuoka Pref.)
Construction Term : 1994/2 ~ 1998/3
Contents of the Project
Length of Bridge=322m
Soil Cutting Work=34,257 m³
Bridge Foundation Work(Deep Pileφ3.0~14.5)=200m
Bridge Substructure Work=11Nos
Temporary Jetty Work=5,248m²
Ishinomaki Fire Station under Integrated Administrative Association of a Large Region, Ishinomaki Area (Miyagi Pref.)
Construction Term : 2005/12 ~ 2007/3
Contents of the Project
Base-isolated Structure of Ishinomaki Fire Station
*RC Structure, 3 Stories, Base-isolated Structure (Single-Story, Steel Structure Garage):
Building Area=1,968.60m², Total Floor Area=3,811.75m²
*Headquarter (Single-Story, Steel Structure Garage):
Building Area=361.11m², Total Floor Area=335.21m²
*Main Training Building (RC Structure, 4 Stories:
Building Area=47.17m², Total Floor Area=129.60m²
*Sub Training Building-A (RC Structure, 2 Stories:
Building Area=127.24m², Total Floor Area=240.00m²
*Sub Training Building-B (RC Structure, 2 Stories)
Building Area=30.33m², Total Floor Area=108.00m²
Park Sanrian- Hakatanomori Ⅰ・Ⅱ (Fukuoka Pref.)
Stage Ⅰ
Construction Term : 2002/4 ~ 2003/3
Contents of the Project
RC Structure, 10 Stories above and 1 under the ground
Total Floor Area=15,931.74m²
Stage Ⅱ
Construction Term : 2004/9 ~ 2006/3
Contents of the Project
RC Structure, 11 Stories
Total Floor Area=16,717.14m²
Kuchinotsu Elementary School (Nagasaki Pref.)
Construction Term : 2003/9 ~ 2005/2
Contents of the Project
RC Structure, 2 Stories
Total Floor Area=5,168.24m²